Time to launch · Hyvä launch
14–15working days
Projected finish between 3 Nov 2026 and 4 Nov 2026.
Milestone progress
Velocity measured over the last 30 days (14 Sep 2026 to 14 Oct 2026, 23 working days).
Time to launch · Hyvä launch
14–15working days
Projected finish between 3 Nov 2026 and 4 Nov 2026.
Time to full completion · all open milestones
20–22working days
Projected finish between 11 Nov 2026 and 13 Nov 2026.
M1
62.5%
5closed
3left
M2
90.7%
49closed
5left
M7
92.9%
13closed
1left
M8
5.9%
1closed
16left
M9
0%
0closed
9left
M10
23.1%
3closed
10left
M11
11.1%
1closed
8left
M12
94.1%
48closed
3left
M13
0%
0closed
1left
M14
61%
25closed
16left
M15
no issues yet
0closed
0left
Production
0%
0closed
1left
97 issues closed between 2 Sep 2026 and 14 Oct 2026.
Seven-day buckets ending on the generation date, each labelled by its first day. “Other” is issues in milestones not shown on this page, or in no milestone.
10
2 Sep
19
9 Sep
8
16 Sep
17
23 Sep
11
30 Sep
32
7 Oct
| Milestone | 2 Sep | 9 Sep | 16 Sep | 23 Sep | 30 Sep | 7 Oct | Total |
|---|---|---|---|---|---|---|---|
| M7 | · | · | · | 1 | 6 | 3 | 10 |
| M12 | 2 | · | 2 | · | 1 | 4 | 9 |
| M14 | · | · | · | · | 1 | 24 | 25 |
| M11 | · | · | · | · | · | 1 | 1 |
| M8 | · | · | · | · | 1 | · | 1 |
| Other | 8 | 19 | 6 | 16 | 2 | · | 51 |
| All issues | 10 | 19 | 8 | 17 | 11 | 32 | 97 |
Each figure below assumes the whole team's current throughput goes to that group alone. Two rollups cannot both be true at once, and they cannot be added together.
M7, M8, M9, M11, M14
14–15working days
Projected finish between 3 Nov 2026 and 4 Nov 2026.
Assumes the whole team's current throughput goes to Hyvä launch and to nothing else. It is not an independent forecast, and it cannot be added to another rollup on this page.
Listed in the order the collector emitted them: measured estimates first, ordered by how soon they finish, with borrowed estimates last so the weakest numbers never head the list.
Extend the Hyvä implementation from MetalCloak to all four sibling stores (Carbon Offroad, KMS, Rocksport, Jobber Portal).
Estimated working days remaining
1–3working days
Projected finish between 15 Oct 2026 and 19 Oct 2026.
Measured from 10 closures across 4 active days in the window (eight or more closures measured inside the window).
Last closure 7 Oct 2026, 23:19 UTC.
Make a fresh clone of this repository reach five verified working storefronts for a remote developer who has only their Gitea identity, via one interactive command, on Linux and WSL2.
Estimated working days remaining
2–10working days
Projected finish between 16 Oct 2026 and 28 Oct 2026.
Measured from 7 closures across 4 active days in the window (three to seven closures measured inside the window).
Last closure 8 Oct 2026, 22:39 UTC.
Pre-launch theme-fit and compatibility work for CMS pages, CMS blocks, the homepage redesign, and content surfaces. Split out of M6, which is now login/account only. Per-store repeat of this sweep stays in M7 (#104).
Estimated working days remaining
4–15working days
Projected finish between 20 Oct 2026 and 4 Nov 2026.
Measured from 25 closures across 6 active days in the window (eight or more closures measured inside the window).
Gitea's own counters disagree with this list: pull requests are attached to this milestone. Only issues are counted here.
Last closure 14 Oct 2026, 04:22 UTC.
Post-launch effort: a Hyvä-consistent CMS pattern library so employees create new CMS pages in the admin panel that match the launched UI. Planned via the Wayfinder map in this milestone; implementation issues are cut when the map's decisions are resolved. Sequenced after M6/M7 (launched theme + fixed CMS pages are the raw material).
Estimated working days remaining
8–184working days
Projected finish between 26 Oct 2026 and 29 Jun 2027.
Measured from 1 closure across 1 active day in the window (one or two closures measured inside the window).
Last closure 12 Oct 2026, 22:10 UTC.
Execute the minimum release gate. Validate all release-blocking flows against staging. Deliver CI/CD foundations. Produce a signed-off go/no-go checklist for the Hyvä Launch.
Estimated working days remaining
16–368working days
Projected finish between 5 Nov 2026 and 13 Mar 2028.
Measured from 1 closure across 1 active day in the window (one or two closures measured inside the window).
Last closure 5 Oct 2026, 23:36 UTC.
Enhancements intentionally deferred until after the Hyvä Launch. Work in this milestone does not block launch; existing release-blocking storefront behavior must still be preserved. Includes the future move from native HTML navigation content to visual authoring with Hyvä CMS / Menu Builder.
Estimated working days remaining
Complete
Nothing outstanding.
This milestone has closed nothing inside the window, so the estimate above is borrowed: it is the median rate of the milestones that are actually moving. It describes what a typical moving milestone would take, not what this one is doing. Treat it as a placeholder.
Performance and caching work deferred until after the Hyvä launch/deployment. Varnish full-page cache behaviour, CDN (Cloudflare) cache-hit rates, and post-launch performance regressions live here.
Estimated working days remaining
1–4working days
Projected finish between 15 Oct 2026 and 20 Oct 2026.
This milestone has closed nothing inside the window, so the estimate above is borrowed: it is the median rate of the milestones that are actually moving. It describes what a typical moving milestone would take, not what this one is doing. Treat it as a placeholder.
Follow-up work from production incidents: land vendor hotfixes in package source, release through the normal dependency workflow, add regression coverage.
Estimated working days remaining
1–4working days
Projected finish between 15 Oct 2026 and 20 Oct 2026.
This milestone has closed nothing inside the window, so the estimate above is borrowed: it is the median rate of the milestones that are actually moving. It describes what a typical moving milestone would take, not what this one is doing. Treat it as a placeholder.
Migrate local development from Scandi CMA / WSL to Warden. Establish a one-command bootstrap, live reload for frontend iteration, a repeatable dataset restore workflow, and a documented environment/secret management approach.
Estimated working days remaining
2–10working days
Projected finish between 16 Oct 2026 and 28 Oct 2026.
This milestone has closed nothing inside the window, so the estimate above is borrowed: it is the median rate of the milestones that are actually moving. It describes what a typical moving milestone would take, not what this one is doing. Treat it as a placeholder.
Achieve high certainty on every release-blocking surface, custom module, and third-party extension before any implementation issues are written.
Estimated working days remaining
3–17working days
Projected finish between 19 Oct 2026 and 6 Nov 2026.
This milestone has closed nothing inside the window, so the estimate above is borrowed: it is the median rate of the milestones that are actually moving. It describes what a typical moving milestone would take, not what this one is doing. Treat it as a placeholder.
Post-launch program to achieve Technical Consent Readiness across MetalCloak, Carbon Offroad, KMS, Rocksport, and Jobber Portal. Establish strict opt-in controls, synchronized cross-domain preferences, consent-aware optional technology loading, and evidence-based verification. This milestone does not block the Hyvä Launch and does not constitute legal certification.
Estimated working days remaining
6–30working days
Projected finish between 22 Oct 2026 and 25 Nov 2026.
This milestone has closed nothing inside the window, so the estimate above is borrowed: it is the median rate of the milestones that are actually moving. It describes what a typical moving milestone would take, not what this one is doing. Treat it as a placeholder.
Post-launch modernization of analytics across MetalCloak, Carbon Offroad, KMS, Rocksport, and Jobber Portal. Delivers a reliable measurement foundation after M9 consent hardening; it does not block the Hyvä Launch.
Estimated working days remaining
6–33working days
Projected finish between 22 Oct 2026 and 30 Nov 2026.
This milestone has closed nothing inside the window, so the estimate above is borrowed: it is the median rate of the milestones that are actually moving. It describes what a typical moving milestone would take, not what this one is doing. Treat it as a placeholder.
The slow end spreads a milestone's closures over every working day in the window: the pace it holds if it keeps the share of attention it has been getting. The fast end spreads them only over the days that actually saw a closure: the pace it holds if nothing else is worked on. The truth sits between them. Neither end is a commitment.
A milestone that closed nothing inside the window has no rate of its own, so it borrows the median rate of the milestones that are moving. That says what a typical moving milestone would take, not what this one is doing. Those cards are drawn weaker on purpose.
Pull requests are excluded from every count and every rate. Where Gitea's own milestone counters disagree with the issue list, the card says so.
Monday to Friday, with no allowance for holidays, leave, or the days already lost to whatever else is on. Projected dates advance by working days from the generation date above.